Agia Pelagia Beach Restoration Will Move Forward After Years of Delays

A €3.2 million project to combat coastal erosion and restore Agia Pelagia beach has entered the tender stage, with work potentially beginning in 2027. (Photo: Argophilia)

  • A €3.2 million project to stop erosion at Agia Pelagia Beach has started the tender phase.
  • Included in the plan are a 70-meter-long submerged breakwater, artificial reefs, and beach nourishment.
  • In some areas, the new beach may grow up to 40 meters wide.
  • It is anticipated that if there are no appeals or other delays, the contract will be signed in early 2027.

After many years of bureaucratic delay, a major project to prevent further erosion of Agia Pelagia Beach in the Municipality of Malevizi is finally starting.

This project is costing €3.2 million and is designed to help protect the shoreline, restore a portion of the beach, and improve the quality of life for those living near one of the area’s most popular tourist destinations.

One of the key elements of this project is the creation of a 70 meter long submerged breakwater that will help dissipate waves before they hit the shore. Additionally, the plan includes artificial reefs and beach nourishment. When finished, the restored beach is expected to be up to 40 meters wide in certain areas.

At present, the tender process is taking place.

Mayor of Malevizi Menelaos Bokeas stated that this project has been a top priority for the local community since 2019, when preparation work began, and efforts were made to obtain financing.

Almost Half of the Beach Has Gone

Due to severe coastal erosion, Agia Pelagia Beach has lost nearly half of its original length, especially the western side of the beach.

According to Bokeas, nearly half of the beach has been lost compared to what it used to be. This loss has created difficulties for both residents and the local businesses that rely on tourism.

“Nearly half of the beach does not exist today. To us, obtaining funding first was our largest objective,” said Bokeas.

The Mayor further stated that the purpose of the restoration project is to enhance the future of the tourism industry in the area, while allowing local businesses to increase their ability to serve visitors.

The project will utilize beach nourishment and underwater structures to lessen the impact of waves and currents on the shoreline.

“In addition to adding thousands of cubic meters of sand, we have included artificial reefs and breakwaters within this project to protect the coastline from underwater currents and erosion,” said Bokeas.

Contract May Be Signed in Early 2027

It is expected that bid submissions will be due by mid-December.

If there are no appeals or other delays, the Municipality anticipates signing the contract during the first quarter of 2027 or, at worst, during the first four months of 2027.

The Municipality is hoping that construction can begin prior to the start of the 2027 summer season; however, timing will ultimately depend upon when all necessary procedural requirements have been met and when the construction schedule can be determined.

Bokeas stated that it is currently too early to tell how long each phase of construction will take.

The Mayor stated that this restoration project is something that Agia Pelagia residents have waited for a long time and thanked the Region of Crete, the Ministry of Interior, residents and Municipal employees for assisting in securing funding and moving the project through the required procedures.

Flood Protection Measures Planned as Well

The coastal project is just one component of a larger series of proposed interventions in Agia Pelagia.

The Municipality is currently developing a separate project that will involve installing flood control barriers to protect the area from flooding. According to Bokeas, this project is very close to being added to a funding program.

The Municipality is also conducting studies into improving the management and protection of the shoreline surrounding the channel in Agia Pelagia. According to Bokeas, the channel’s primary current problem relates to appearance rather than its function as a flood control measure.

Additional interventions are planned through the Municipality’s Special Urban Plan, which will establish a more comprehensive planning framework for Agia Pelagia and the entire Municipality of Malevizi.

New Independent Water Supply Planned as Well

Another project that is rapidly approaching implementation involves establishing an independent water supply system for Agia Pelagia.

The Municipality has completed a feasibility study for a new independent water supply system that will connect directly to the Skafidaras desalination plant.

The plant reportedly has a capacity of 3,000 cubic meters of water per day, with the anticipated connection providing a direct source of water for Agia Pelagia.

With both coastal erosion and increased visitor demands as issues facing a resort such as Agia Pelagia, providing beach protection, flood management, and water infrastructure are all parts of a larger effort aimed at supporting Agia Pelagia’s future as a tourism destination.

Categories: Crete Featured
Mihaela Lica Butler: A former military journalist, <a href="https://www.facebook.com/mihaelalicabutler">Mihaela Lica-Butler</a> owns and is a senior partner at Pamil Visions PR and editor at Argophilia Travel News. Her credentials speak for themselves: she is a cited authority on search engine optimization and public relations issues, and her work and expertise were featured on BBC News, Reuters, Yahoo! Small Business Adviser, Hospitality Net, Travel Daily News, The Epoch Times, SitePoint, Search Engine Journal, and many others. Her books are available on <a href="https://amzn.to/2YWQZ35">Amazon</a>